Excercise 01

Chapter 01: Question 02

Sri Lankas one of leading IT service company Eureka Technology has planned to commence a project to add the entire company personal computers to the domain and limit the user permissions according to the new company policy. The Eureka Technologies IT Manager Mr. Suleiman Razmik is interviewed as he is selected as the project manager for the project



Question: What is the main objective of the Project?

Answer: The main goal of the project is to add 1500 personal computers to the domain which help to manage the entire PC with centralized management and limit access permission to the resources according to the level and department of the company.

Question: What is the duration you expect to complete the project and how much it will cost for it?

Answer: The entire process is expected to complete within six months under a budget of 500,000 US dollars and a further 40,000 $ which is expected as the maintenance cost for one year after the completion.


Question: What are the steps and activities you expect to carry out prior to the project implementation

Answer: First of all we expect to survey and collect relevant information about the present workgroup computers and we plan to carry out the project based on departments such as HR, technical division, finance division and other divisions phase by phase one after the other respectively.