Thursday, March 27, 2008

Excercise 04

Chapter 03 : question 01

Study the WBS and Gantt charts provided in Figures 3-3 and 3-4. Enter the WBS into Project 2003, indenting tasks as shown to create the WBS hierarchy. Then enter durations and dependencies to try to reproduce the Gantt chart .

Sunday, March 16, 2008

Excercise 03

Chapter 04 : Question 04

Prepare a Project charter for the Recreation and Wellness Intranet Project. Assume the project will take six months to complete and cost about $200,000.Use the project charter template provided in this text and the sample project charter provide in chapter 3 as a guide.

Answer:


Project Title: Manage Your Health (MYH) Recreation and Wellness Project.

Project Start Date: April 10th 2007. Project End Date: October 10th 2007.

Project Manager: Tony Prince, 555-4755, tonyprince@myh.com

Budget Information: The management has allocated $200,000 for this project.

Project Objectives:

To develop a user-friendly Intranet Website in 6 months to allow employee registration for company sponsored events and classes.

Approach:

Develop a survey to determine critical features of the new intranet site and solicit input from all employees to make sure it is user friendly

Review templates and examples of project management documents based on previous system analysis within the company

Develop the intranet site using and iterative approach, soliciting a great deal of user feedback.

Research software to provide security for online transactions, manage inputs and facilitate the user registration in a user friendly manner.


Roles and Responsibilites

NAME -----------------------------ROLE ---------------------RESPONSIBILY
------------------------------------------------------------------------------------
Alec Stuart -------------------CEO ------------------------Project Sponsor, Monitor Project
Tony Prince ------------------Project Manager ------------Plan and Execute Project
Irshad Barakath -------------Team Member --------------Information and Surveys
Shaheer Siddeeq -------------Team Member-------------- Website Administrator
Christian Bale -----------------QA -------------------------Quality Assurance and Testing


Comments: Handwritten or Type comments from above stake holders (if applicable).

I will coordinate, plan and execute the project and expect to complete the project within the timelines as needed by the management of MYH. I will have my Team members to support the project as needed - Tony Prince

I will ensure that the website delivered will be assessed for security especially for online transactions made by employees and well as emphasize on user friendliness. – Christian Bale

Excercise 02

Chapter 02 : Question 05

Summary of article about importance of top management support for successful informataion technolgy project ?

The number one success factor of any project is executive support or the support of top management. If company executives do not understand or care about the project, they will not allocate the time, money or resources which needs to make the project successful

Most of the co-operate executives are aware of the need for IT security, however if management is still not taking the IT security seriously enough you will have to face many problems in the issues and the preventive actions to be taken on the working project.

When considering a IT security project in the organization the cost of labor to asses, plan, implement, manage monitor is expensive other than the hardware and software needs. Without the executive support for IT security Project it will be hard to get IT security Budget approved.

Without the executive support , the project initiatives will ultimately fail because the organization will allocate time and resources to other projects. If the executive team does not understand or value the project initiatives it will be an uphill battle. However this can be only avoided when there is a support and the active involvement at the top.

Reference: Syngress IT Security Project Management Handbook, by Susan Snedakar

Monday, March 10, 2008

Excercise 01

Chapter 01: Question 02

Sri Lankas one of leading IT service company Eureka Technology has planned to commence a project to add the entire company personal computers to the domain and limit the user permissions according to the new company policy. The Eureka Technologies IT Manager Mr. Suleiman Razmik is interviewed as he is selected as the project manager for the project



Question: What is the main objective of the Project?

Answer: The main goal of the project is to add 1500 personal computers to the domain which help to manage the entire PC with centralized management and limit access permission to the resources according to the level and department of the company.

Question: What is the duration you expect to complete the project and how much it will cost for it?

Answer: The entire process is expected to complete within six months under a budget of 500,000 US dollars and a further 40,000 $ which is expected as the maintenance cost for one year after the completion.


Question: What are the steps and activities you expect to carry out prior to the project implementation

Answer: First of all we expect to survey and collect relevant information about the present workgroup computers and we plan to carry out the project based on departments such as HR, technical division, finance division and other divisions phase by phase one after the other respectively.